Project Summary

The City Walk Center is the core of shopping and dining areas which serves Universal City visitors. The City Walk Center Court Fountain Renovation and Expansion Project Scope included Field verification of existing conditions at both water features, equipment vault, electrical room and trash compactor Area and the upgrade of existing electrical service to accommodate new lighting controls, added equipment and power supply to the vault equipment. Review of WET Company drawings and to select transformers and provide and specify mechanical equipment to ventilate and air-condition the vault and comply with any additional OSHA and Agency requirement as well as construction phase oversight was required as part of the scope.